Malahat Macro-Network Planning

The ultimate goal of Malahat Macro-Network Planning is to have the entire Nation, houses and offices, connected together in a mesh layout. This enables Malahat to retain ownership of our networking infrastructure while providing free, fast internet access to our members. Other benefits include security oversight, IoT opportunities, and significant cost savings in the long run.

This project will roll out in phases and is subject to change. Phases can be implemented simultaneously and the order is not important.

Phase 1 - Inter-building connectivity in upper cluster

DJI_0004_ZVWnqAM2 Zoom in copy.png

We currently have all 5 upper cluster addresses connected via conduit as shown above. The external connection comes from Shaw and runs into 3 Kwunew Kwasun Lane. From there, the connectivity is distributed to 5 & 7 Kwunew Kwasun Lane, and 1121 Jesken Road. 1 Kwunew Kwasun still needs to be connected to the network, but the conduit is installed and ready to go. See below for a more zoomed out version of the above photo.

DJI_0004_ZVWnqAM2  V2 copy.png

These connections are currently based on copper cabling (CAT6) and can support speeds approaching 1Gbps up to 300ft. The connection between 3 KKL and 7KKL is longer than 300ft and is subject to a small amount of bandwidth degradation. To complete Phase 1, we will need to replace these copper cables with fibre optic cables which have far higher range and bandwidth limitations.

Estimated cost to replace copper cables with fibre: $10,000