Malahat Macro-Network Planning
Phase 1 - Inter-building connectivity in upper cluster
We now have all 5 upper cluster addresses connected via conduit as shown above. The external connection comes from Shaw and runs into 3 Kwunew Kwasun Lane. From there, the connectivity is distributed to 5 & 7 Kwunew Kwasun Lane, and 1121 Jesken Road. 1 Kwunew Kwasun still needs to be connected to the network, but the conduit is installed and ready to go. See below for a more zoomed out version of the above photo.

